Expanded capacity in Kilforsen

About this project

In order to maintain personal and operational safety and increase transmission capacity in the area, the transmission grid section in IK33 Kilforsen needs to be renewed by constructing a new UT68 Kilforsen approximately half a kilometre northeast of the existing substation.

The contract covers earthworks and concrete work for five pipe foundations, as well as other earthworks and service work required for the completion of the contract.

Fact

Client
Vattenfall Services Nordic AB

Construction year
2025-2026

Type of contract
Construction contract

Hamnstadens services

Concrete works for transmission line foundations
Excavation and filling work
Groundwork
Grounding
Underpinning

Our projects

Contact person for this project

Erik Lindmark

Construction Engineer