Updated substation for SVK

About this project

The existing 400 kV substation will be renovated and replaced by a new 400 kV transmission network facility, UT292 Letsi. The facility will consist of a 400 kV substation with a control building.

The contract covers preparatory ground and concrete work for the station area for the end customer SVK for project UT292 Letsi in the municipality of Jokkmokk. 

Fact

Client
Vattenfall Services Nordic AB

Type of contract
Construction contract

Hamnstadens services

Excavation and terracing
Foundation work
Concrete works for transmission line foundations
Excavation and filling work
Electrical work
Water and sewerage work

Our projects

Contact person for this project

Mattias Johansson